When Contractual Construction Becomes Contractual Rewriting
![]() |
| pic courtesy : Supreme Court of India |
The Limits of
Arbitral Interpretation
Shreeram Builders v. Upendra Kantilal Thanawala & Ors.
2026 INSC 1176 | Civil Appeal Nos. 9817–9818 of 2024 | Decided on 29 October
2026
An
arbitral tribunal is empowered to interpret a contract, reconcile its
provisions and give effect to the commercial intention of the parties. However,
that authority does not extend to reconstructing the bargain itself. The
distinction between interpreting contractual obligations and substituting them
with obligations of the tribunal’s own making forms the central theme of the
Supreme Court’s decision in Shreeram Builders v. Upendra Kantilal Thanawala.
The
judgment examines the statutory obligation under Section 28(3) of the
Arbitration and Conciliation Act, 1996, and reiterates that arbitral autonomy
cannot become a justification for disregarding the very contract from which the
tribunal derives its jurisdiction.
1. Factual Details
The dispute arose from an
Agreement for Development dated 6 August 2003, executed between members of the
Thanawala family, owners of an undivided 2/9th share in three adjoining parcels
of land at Panchpakhadi, Thane, and Shreeram Builders and its partners.
The agreement
contemplated development of the owners’ share for consideration calculated at
₹915 per square foot of the projected Floor Space Index (FSI). However, it was
not a conventional development arrangement involving a landowner’s entitlement
to a proportionate share of the constructed area. It also contemplated eventual
conveyance of the owners’ interest in the property to the developer or its
nominee.
The agreement prescribed
a carefully structured sequence of reciprocal obligations, including payment of
consideration in ten instalments, procurement of municipal sanctions,
determination of additional FSI and eventual execution of a conveyance. Time was
expressly declared to be of the essence. Clauses 53 and 54 also provided for
termination upon default and the consequential obligation to refund
consideration where construction had not commenced on the owners’ share.
Following disputes
concerning delayed instalments and alleged contractual defaults, the owners
terminated the agreement by notice dated 9 April 2008. The matter proceeded to
arbitration.
By a majority award dated
10 December 2011, the tribunal declared the termination illegal and granted
specific performance, directing the claimants to deposit ₹10,91,30,164. It also
adopted an enhanced rate of ₹5,490 per square foot, six times the originally
stipulated rate, and granted alternative damages.
The award survived the
initial challenge under Section 34 before the Principal District Judge, Thane.
However, the Bombay High Court, exercising appellate jurisdiction under Section
37, set aside the majority award on 5 March 2024, principally finding that the
arbitrators had disregarded the express contractual provisions.
The Supreme Court upheld
the High Court’s conclusion. Nevertheless, it found that the owners themselves
had failed to honour their obligation to refund the consideration following
termination, necessitating separate directions under Article 142 of the Constitution.
2. Legal Issues
A. Whether the
nomenclature of an agreement determines its legal character?
The agreement was titled an
‘Agreement for Development’, but the majority tribunal treated it as an
agreement to sell, while the High Court adopted the contrary view.
The Supreme Court considered
the agreement to be a complex commercial arrangement contemplating both
development and eventual conveyance. More importantly, it held that
conclusively labelling the document was not essential to resolving the dispute.
What mattered was the sequence of obligations expressly stipulated by the
parties.
This is an important aspect
of the judgment: the Court shifted the focus from the classification of the
instrument to the enforceability of the obligations actually undertaken.
B. Whether Section 28(3)
permits an arbitral tribunal to depart from express contractual stipulations?
Section 28(3) mandates that
an arbitral tribunal take into account the terms of the contract and applicable
trade usages while making its award.
The Supreme Court identified
multiple departures from the agreement. The tribunal had directed conveyance
without ensuring payment of the entire consideration, which remained
indeterminate because the final FSI and other additional components had not been
determined. It had also included portions of property expressly excluded from
the agreement, thereby affecting the interests of co-owners who were not
parties to the arbitration.
Further, amounts allegedly
paid under an earlier Memorandum of Understanding were adjusted despite Clause
51 expressly superseding previous agreements. The tribunal also introduced a
sixfold enhancement of the agreed rate without a contractual basis or reasoned
computation.
The Court held that these
were not merely alternative interpretations of contractual provisions. They
amounted to replacing the parties’ bargain with a new arrangement.
C. Whether acceptance of
delayed instalments amounts to waiver of the time stipulation?
The Court drew a significant
distinction between condonation of individual defaults and abandonment of the
contractual stipulation that time was of the essence.
The owners’ acceptance of
the first six delayed instalments without protest, coupled with their failure
to issue notices under Clause 7, had the effect of curing those particular
defaults. It did not, however, extinguish the time stipulation for subsequent
payments.
Consequently, past
indulgence could not be converted into a perpetual obligation upon the owners
to accept payments irrespective of the contractual deadlines.
D. What is the
permissible scope of judicial interference under Sections 34 and 37?
Relying upon the
Constitution Bench decision in Gayatri Balasamy v. ISG Novasoft Technologies
Ltd., the Supreme Court reiterated that the appellate jurisdiction under
Section 37 is coterminous with the jurisdiction exercised under Section 34.
It also clarified that the
unamended Section 34 governed the present dispute, since the applications
challenging the award had been filed before 23 October 2015.
The Court reaffirmed that
contractual interpretation ordinarily belongs to the arbitrator. A plausible
interpretation cannot be displaced merely because a court prefers another.
However, where the tribunal disregards express contractual provisions or adopts
an interpretation that no fair-minded or reasonable person could accept,
interference is justified.
The critical distinction is
between correcting an erroneous interpretation and correcting an award that
effectively creates a different contract.
E. Whether the owners
could retain consideration after terminating the agreement?
The judgment concludes with
an important qualification. Although the majority award could not be sustained,
the owners had themselves failed to comply with Clause 54, which required
repayment of the consideration received when no construction had commenced on
their share.
Invoking Article 142, the
Supreme Court directed repayment of the amounts received, together with simple
interest at 9% per annum from the respective dates of payment until actual
refund. The amounts deposited by the appellant in court were also directed to
be returned with accrued interest.
This ensured that setting
aside the award did not result in an unjustified financial advantage to the
owners.
3. Cases Referred To
The judgment draws upon
an established line of authorities governing contractual interpretation, patent
illegality and the permissible limits of judicial review.
- Sasan Power
Ltd. v. North American Coal Corporation (India) Ltd. (2016) 10
SCC 813: The legal character of an agreement
is determined by the rights and obligations created under it, rather than
merely by its nomenclature.
- Renusagar Power
Co. Ltd. v. General Electric Co. (1994) Supp 1 SCC 644 and
ONGC Ltd. v. Saw Pipes Ltd. (2003) 5 SCC 705: These decisions explain the development of the public policy
doctrine and the recognition of patent illegality as a ground for setting
aside arbitral awards under the unamended Section 34.
- Associate
Builders v. Delhi Development Authority (2015) 3 SCC 49 and UHL Power
Company Ltd. v. State of Himachal Pradesh (2022) 4 SCC 11: These authorities establish that a plausible interpretation of
a contract by an arbitrator ordinarily deserves judicial deference.
- Ssangyong
Engineering & Construction Co. Ltd. v. NHAI (2019) 15 SCC
131, SEAMEC Ltd. v. Oil India Ltd. (2020) 5 SCC 164 and OPG
Power Generation Pvt. Ltd. v. Enexio Power Cooling Solutions India
Pvt. Ltd. (2025) 2 SCC 417: These
decisions address the impermissibility of introducing contractual terms
that the parties never agreed upon and the consequences of an
interpretation that is not reasonably sustainable.
- Gayatri
Balasamy v. ISG Novasoft Technologies Ltd. (2025) 7 SCC 1: The Constitution Bench decision was relied upon to explain the
scope of appellate jurisdiction under Section 37.
- Basant Singh v.
Janki Singh (AIR 1967 SC 341): Relevant to the
evidentiary value of admissions made by parties in earlier proceedings
concerning the same subject matter. The Court also considered Ramabai
Shriniwas Nadgir v. Government of Bombay (AIR 1941 Bom 144) and Dattatraya
Shripati Mohite v. Shankar Ishwara Mohite (AIR 1960 Bom 153) in this
context.
The judgment also
discusses Centrotrade Minerals & Metals Inc. v. Hindustan Copper
Ltd., Delhi Development Authority v. R.S. Sharma & Co., ONGC
Ltd. v. Western Geco International Ltd. and BCCI v. Kochi Cricket
Pvt. Ltd., among other authorities. The Bombay High Court’s reliance on BCCI
v. Deccan Chronicle Holdings Ltd. (2021 SCC OnLine Bom 834) also forms part
of the judicial history considered by the Supreme Court.
4. Conclusion
The real significance of Shreeram
Builders lies in its articulation of the boundary between arbitral
independence and contractual discipline. An arbitrator is entitled to interpret
a commercial bargain, but cannot assume the role of a contracting party and
introduce terms that alter its essential structure.
The judgment does not dilute
arbitral autonomy or invite courts to undertake a fresh examination of every
contractual interpretation. Rather, it identifies the point at which judicial
restraint must yield: when an award ceases to interpret the agreement and
begins to substitute it.
Equally significant is the
Court’s treatment of the owners’ independent contractual default. By invoking
Article 142 and directing repayment with interest, the Court ensured that the
rejection of an unsustainable arbitral award did not legitimise an equally
unsustainable retention of money.
The decision therefore
reinforces two complementary principles: arbitration must remain faithful to
the contract, and judicial intervention must remain confined to recognised
statutory grounds.
An arbitrator may resolve
the uncertainties of a bargain, but cannot manufacture a different bargain in
the name of doing commercial justice.
--- AI Assisted

Comments
Post a Comment