When Contractual Construction Becomes Contractual Rewriting

 

pic courtesy : Supreme Court of India

The Limits of Arbitral Interpretation

Shreeram Builders v. Upendra Kantilal Thanawala & Ors.
2026 INSC 1176 | Civil Appeal Nos. 9817–9818 of 2024 | Decided on 29 October 2026

An arbitral tribunal is empowered to interpret a contract, reconcile its provisions and give effect to the commercial intention of the parties. However, that authority does not extend to reconstructing the bargain itself. The distinction between interpreting contractual obligations and substituting them with obligations of the tribunal’s own making forms the central theme of the Supreme Court’s decision in Shreeram Builders v. Upendra Kantilal Thanawala.

The judgment examines the statutory obligation under Section 28(3) of the Arbitration and Conciliation Act, 1996, and reiterates that arbitral autonomy cannot become a justification for disregarding the very contract from which the tribunal derives its jurisdiction.

1. Factual Details

The dispute arose from an Agreement for Development dated 6 August 2003, executed between members of the Thanawala family, owners of an undivided 2/9th share in three adjoining parcels of land at Panchpakhadi, Thane, and Shreeram Builders and its partners.

The agreement contemplated development of the owners’ share for consideration calculated at ₹915 per square foot of the projected Floor Space Index (FSI). However, it was not a conventional development arrangement involving a landowner’s entitlement to a proportionate share of the constructed area. It also contemplated eventual conveyance of the owners’ interest in the property to the developer or its nominee.

The agreement prescribed a carefully structured sequence of reciprocal obligations, including payment of consideration in ten instalments, procurement of municipal sanctions, determination of additional FSI and eventual execution of a conveyance. Time was expressly declared to be of the essence. Clauses 53 and 54 also provided for termination upon default and the consequential obligation to refund consideration where construction had not commenced on the owners’ share.

Following disputes concerning delayed instalments and alleged contractual defaults, the owners terminated the agreement by notice dated 9 April 2008. The matter proceeded to arbitration.

By a majority award dated 10 December 2011, the tribunal declared the termination illegal and granted specific performance, directing the claimants to deposit ₹10,91,30,164. It also adopted an enhanced rate of ₹5,490 per square foot, six times the originally stipulated rate, and granted alternative damages.

The award survived the initial challenge under Section 34 before the Principal District Judge, Thane. However, the Bombay High Court, exercising appellate jurisdiction under Section 37, set aside the majority award on 5 March 2024, principally finding that the arbitrators had disregarded the express contractual provisions.

The Supreme Court upheld the High Court’s conclusion. Nevertheless, it found that the owners themselves had failed to honour their obligation to refund the consideration following termination, necessitating separate directions under Article 142 of the Constitution.

2. Legal Issues

A. Whether the nomenclature of an agreement determines its legal character?

The agreement was titled an ‘Agreement for Development’, but the majority tribunal treated it as an agreement to sell, while the High Court adopted the contrary view.

The Supreme Court considered the agreement to be a complex commercial arrangement contemplating both development and eventual conveyance. More importantly, it held that conclusively labelling the document was not essential to resolving the dispute. What mattered was the sequence of obligations expressly stipulated by the parties.

This is an important aspect of the judgment: the Court shifted the focus from the classification of the instrument to the enforceability of the obligations actually undertaken.

B. Whether Section 28(3) permits an arbitral tribunal to depart from express contractual stipulations?

Section 28(3) mandates that an arbitral tribunal take into account the terms of the contract and applicable trade usages while making its award.

The Supreme Court identified multiple departures from the agreement. The tribunal had directed conveyance without ensuring payment of the entire consideration, which remained indeterminate because the final FSI and other additional components had not been determined. It had also included portions of property expressly excluded from the agreement, thereby affecting the interests of co-owners who were not parties to the arbitration.

Further, amounts allegedly paid under an earlier Memorandum of Understanding were adjusted despite Clause 51 expressly superseding previous agreements. The tribunal also introduced a sixfold enhancement of the agreed rate without a contractual basis or reasoned computation.

The Court held that these were not merely alternative interpretations of contractual provisions. They amounted to replacing the parties’ bargain with a new arrangement.

C. Whether acceptance of delayed instalments amounts to waiver of the time stipulation?

The Court drew a significant distinction between condonation of individual defaults and abandonment of the contractual stipulation that time was of the essence.

The owners’ acceptance of the first six delayed instalments without protest, coupled with their failure to issue notices under Clause 7, had the effect of curing those particular defaults. It did not, however, extinguish the time stipulation for subsequent payments.

Consequently, past indulgence could not be converted into a perpetual obligation upon the owners to accept payments irrespective of the contractual deadlines.

D. What is the permissible scope of judicial interference under Sections 34 and 37?

Relying upon the Constitution Bench decision in Gayatri Balasamy v. ISG Novasoft Technologies Ltd., the Supreme Court reiterated that the appellate jurisdiction under Section 37 is coterminous with the jurisdiction exercised under Section 34.

It also clarified that the unamended Section 34 governed the present dispute, since the applications challenging the award had been filed before 23 October 2015.

The Court reaffirmed that contractual interpretation ordinarily belongs to the arbitrator. A plausible interpretation cannot be displaced merely because a court prefers another. However, where the tribunal disregards express contractual provisions or adopts an interpretation that no fair-minded or reasonable person could accept, interference is justified.

The critical distinction is between correcting an erroneous interpretation and correcting an award that effectively creates a different contract.

E. Whether the owners could retain consideration after terminating the agreement?

The judgment concludes with an important qualification. Although the majority award could not be sustained, the owners had themselves failed to comply with Clause 54, which required repayment of the consideration received when no construction had commenced on their share.

Invoking Article 142, the Supreme Court directed repayment of the amounts received, together with simple interest at 9% per annum from the respective dates of payment until actual refund. The amounts deposited by the appellant in court were also directed to be returned with accrued interest.

This ensured that setting aside the award did not result in an unjustified financial advantage to the owners.

3. Cases Referred To

The judgment draws upon an established line of authorities governing contractual interpretation, patent illegality and the permissible limits of judicial review.

  1. Sasan Power Ltd. v. North American Coal Corporation (India) Ltd. (2016) 10 SCC 813: The legal character of an agreement is determined by the rights and obligations created under it, rather than merely by its nomenclature.
  2. Renusagar Power Co. Ltd. v. General Electric Co. (1994) Supp 1 SCC 644 and ONGC Ltd. v. Saw Pipes Ltd. (2003) 5 SCC 705: These decisions explain the development of the public policy doctrine and the recognition of patent illegality as a ground for setting aside arbitral awards under the unamended Section 34.
  3. Associate Builders v. Delhi Development Authority (2015) 3 SCC 49 and UHL Power Company Ltd. v. State of Himachal Pradesh (2022) 4 SCC 11: These authorities establish that a plausible interpretation of a contract by an arbitrator ordinarily deserves judicial deference.
  4. Ssangyong Engineering & Construction Co. Ltd. v. NHAI (2019) 15 SCC 131, SEAMEC Ltd. v. Oil India Ltd. (2020) 5 SCC 164 and OPG Power Generation Pvt. Ltd. v. Enexio Power Cooling Solutions India Pvt. Ltd. (2025) 2 SCC 417: These decisions address the impermissibility of introducing contractual terms that the parties never agreed upon and the consequences of an interpretation that is not reasonably sustainable.
  5. Gayatri Balasamy v. ISG Novasoft Technologies Ltd. (2025) 7 SCC 1: The Constitution Bench decision was relied upon to explain the scope of appellate jurisdiction under Section 37.
  6. Basant Singh v. Janki Singh (AIR 1967 SC 341): Relevant to the evidentiary value of admissions made by parties in earlier proceedings concerning the same subject matter. The Court also considered Ramabai Shriniwas Nadgir v. Government of Bombay (AIR 1941 Bom 144) and Dattatraya Shripati Mohite v. Shankar Ishwara Mohite (AIR 1960 Bom 153) in this context.

The judgment also discusses Centrotrade Minerals & Metals Inc. v. Hindustan Copper Ltd., Delhi Development Authority v. R.S. Sharma & Co., ONGC Ltd. v. Western Geco International Ltd. and BCCI v. Kochi Cricket Pvt. Ltd., among other authorities. The Bombay High Court’s reliance on BCCI v. Deccan Chronicle Holdings Ltd. (2021 SCC OnLine Bom 834) also forms part of the judicial history considered by the Supreme Court.

4. Conclusion

The real significance of Shreeram Builders lies in its articulation of the boundary between arbitral independence and contractual discipline. An arbitrator is entitled to interpret a commercial bargain, but cannot assume the role of a contracting party and introduce terms that alter its essential structure.

The judgment does not dilute arbitral autonomy or invite courts to undertake a fresh examination of every contractual interpretation. Rather, it identifies the point at which judicial restraint must yield: when an award ceases to interpret the agreement and begins to substitute it.

Equally significant is the Court’s treatment of the owners’ independent contractual default. By invoking Article 142 and directing repayment with interest, the Court ensured that the rejection of an unsustainable arbitral award did not legitimise an equally unsustainable retention of money.

The decision therefore reinforces two complementary principles: arbitration must remain faithful to the contract, and judicial intervention must remain confined to recognised statutory grounds.

An arbitrator may resolve the uncertainties of a bargain, but cannot manufacture a different bargain in the name of doing commercial justice.



--- AI Assisted

Comments

Popular posts from this blog

New Chapter on CIRP-CI : Creditor Initiated - As per the IBC Amendment Bill, 2025

Permanent Establishment arising out of "Exploration of Natural Resources"

The International Games and ESports Tribunal (IGET) and the RIOT Games Dispute Resolution Initiative